Mumbai’s Belasis Flyover Reopens Early: 130-Year-Old Bridge Rebuilt in Just 15 Months, Big Relief for Commuters

thebombaydurpun
6 Min Read

Belasis Flyover Is Back and Ahead of Schedule

Mumbai commuters finally have a reason to smile. The Belasis Flyover, a crucial east-west connector linking Tardeo, Nagpada and Mumbai Central Station, has been completed in a record-breaking 15 months and six days, much earlier than its original deadline in May.

Located on Jehangir Boman Behram Marg, earlier known as Belasis Road, the flyover’s reopening is expected to restore smooth traffic movement that had been disrupted for nearly two years. Once opened to traffic, it will significantly ease congestion in some of South and Central Mumbai’s busiest corridors.


Why Belasis Flyover Matters to Mumbai

The Belasis Flyover plays a critical role in connecting eastern and western parts of central Mumbai. Its closure had forced motorists to take longer detours, adding to congestion on already crowded roads.

Areas That Will See Immediate Relief

With the flyover ready, traffic pressure is expected to reduce on:

  • Jehangir Boman Behram Marg
  • Dadasaheb Bhadkamkar Marg at Grant Road
  • Patthe Bapurao Marg
  • The Mahalaxmi Station bridge

For daily commuters, taxi drivers, BEST buses, and pedestrians, this translates into shorter travel times and smoother journeys.


A 130-Year-Old British-Era Bridge Rebuilt from Scratch

Why the Old Bridge Had to Go

The original Belasis Bridge was over 130 years old and dated back to the British era. Structural audits had declared it unsafe, making demolition unavoidable.

Instead of patchwork repairs, the Brihanmumbai Municipal Corporation decided on a complete reconstruction, ensuring modern safety standards, higher load capacity, and better pedestrian facilities.


Record-Breaking Timeline: How Was It Done So Fast?

Planning Started in 2024

The work order for the Belasis Flyover was issued in September 2024, and construction officially began on October 1, 2024. From day one, the focus was on speed without compromising quality.

Engineers adopted a segment-wise execution strategy, breaking the massive project into smaller, manageable tasks. Each activity had fixed timelines, and deadlines were strictly monitored.


Teamwork Across Departments Made the Difference

One of the biggest reasons behind the early completion was seamless coordination between multiple agencies.

The BMC’s bridges department handled the core construction work, including girder bracing, deck sheet installation, slab casting, and approach roads. The railway department managed construction over the railway tracks, a task that usually causes major delays in Mumbai projects.

Support from the local ward office and traffic police ensured minimal disruption on surrounding roads and smooth handling of diversions.


Construction Did Not Stop Even During Monsoon

Mumbai’s monsoon season often slows down infrastructure projects, but Belasis Flyover was an exception.

Work continued uninterrupted for four months during the monsoon, a major factor that helped keep the project on track. Engineers adjusted schedules, improved site management, and ensured safety standards were maintained even during heavy rainfall.


Overcoming Challenges Without Delays

Major Obstacles Along the Way

Rebuilding the flyover was not without hurdles. The project faced multiple on-ground challenges, including:

  • Relocation of BEST bus stops
  • Removal of 13 obstructing structures
  • Rehabilitation of affected occupants
  • Demolition of a housing society’s boundary wall
  • Court-related proceedings

Despite these complications, officials ensured that none of these issues caused delays in construction.


Modern Design for Today’s Traffic Needs

Key Features of the New Belasis Flyover

The rebuilt Belasis Flyover has been designed keeping current and future traffic demands in mind.

  • Total length of 333 metres
  • Seven-metre-wide carriageway for smoother vehicular movement
  • Wide footpaths on both sides for pedestrian safety

These improvements aim to balance speed, safety, and accessibility for all road users.


Safety Checks Completed, Opening Soon

The finishing work on the flyover was completed on January 6, 2026. Since then, multiple safety processes have been completed.

Clearances Secured

  • Load testing completed
  • Structural stability certification obtained
  • Safety certification secured

According to Additional Municipal Commissioner Abhijit Bangar, the flyover will be opened to traffic after receiving the final No Objection Certificate from the railway department and coordinating with the traffic police.


BMC Calls It a Model Project

Abhijit Bangar described the Belasis Flyover as a strong example of how complex infrastructure projects can be completed ahead of schedule through disciplined planning and effective execution.

He highlighted that focusing on quality construction while minimising inconvenience to citizens allows the benefits of development to reach people faster. The BMC now plans to replicate this approach across other major infrastructure projects in the city.


What This Means for Mumbaikars

For residents of Tardeo, Nagpada, Mumbai Central, and nearby areas, the reopening of Belasis Flyover brings much-needed relief after nearly two years of traffic chaos.

Shorter travel times, reduced congestion, and safer pedestrian movement will improve daily commuting experiences. More importantly, the project sets a new benchmark for how quickly and efficiently urban infrastructure can be delivered in Mumbai.


A Rare Infrastructure Success Story

In a city often criticised for delayed projects, the early completion of the Belasis Flyover stands out. Rebuilding a century-old bridge in just over 15 months, even during monsoon, shows what is possible with proper coordination, accountability, and commitment.

As Mumbai continues to upgrade its ageing infrastructure, the Belasis Flyover may well serve as a blueprint for faster, smarter, and more commuter-friendly development.